pp108 : Setting Lead Time for an Activity

Setting Lead Time for an Activity

This topic describes the process of setting the Lead Time for an activity.

For the 'Start' event of an activity under the Events section, select the Lead-time attribute under the Attribute Selection section.The
Confirm dialog box appears to select the duration category. Select any of the following:

  • Ideal Lead Time
  • Expected Lead Time
  • Minimum Lead Time
  • Maximum Lead Time

    Based on the selection of the category, their respective values get filled in the Define Conditions and Actions Interface to build the condition expression. For more details on Estimated Lead Time refer to Fields on the Estimated Duration tab Table of Activity Properties Interface.

    Note: The Confirm dialog appears only if any of the fields in the Estimated Lead Time of the ' Estimated Duration ' tab in the properties window of the activity of type 'Task' is filled.